South Lima | Chinese Federation | Sedapal | 60 million sole | 14 months delay | 701 thousand sole | Five Punishments | Villa Maria del Trinfo | Villa El Salvador | Miraflores Saint John | | principle

A delay that could affect thousands. The San Miguel consortium used unauthorized materials and caused a 14-month delay in the delivery of 20 kilometers of pipes for the largest sanitation project in Peru. Sedapal estimates that the fine for this violation would be approximately S/60 million. The work is scheduled to be delivered in August 2025.

WATCH: Minister Hania Perez de Guler on Chinese companies: “There is a kind of cartel at home”

In early August 2021, Cetabal and the Sino-Peruvian consortium signed an agreement to execute the Nua Rinconada, a water and sewage project south of Lima worth about S/1,200 million.

To date, however, the federation has accumulated five fines and a sixth, already on the table, could delay the provision of work that will benefit the 350,000 residents of San Juan de Miraflores, Villa Maria del Trinfo and Villa El Salvador.

truth A San Miguel confederation engineer promises the pipes will arrive in August. (Photo: Peru21)

What are the reasons for previous convictions? Three violations for using unauthorized materials and two for failing to comply with environmental measures. The price of these five is S/701 thousand. However, according to Sedapal’s calculations, the new fine of S/60 million has not yet been applied. Also, delivery of 20 km long iron pipes will lead to a delay of 14 months to major water lines. The total length is 101 kilometers.

Chedapal calculates that this new penalty is equivalent to approximately 5% of the total contract amount. The delivery period for this item has expired in April 2022.

Fourteen months late

“What if the job goes well? Obviously not; If not, there will be no penalty,” he said Peru21 Julio Ramírez, CEDAPAL Program and Mission Manager.

See also  Martha Moyano and Patricia Chirinos: Reasons for the prosecution to investigate them as members of Patricia Benavides' criminal network? | principle

Delay in supply of ductile iron will delay job delivery after August 2025? We asked Ramirez. “If you’re saying this issue could extend the work beyond 2025, then yes, it’s possible if they keep delaying,” he said. Clear, no water.

The State Procurement Act establishes that Sedapal can cancel the contract if it incurs a penalty of 10% of the total contract amount. A Cedapal official indicated that this would happen only if the company delayed the delivery by another year.

In an interview Peru21Carla Cavino, an expert in public administration, assured that such a delay would delay the execution of the task. “A delay of more than a year, how can that not affect delivery? Where are you going to recover in that year and beyond? What are you going to do fast? At what risk and at what cost?,” Kavino questioned. “It is one thing to implement a project in the first year, another to move it to the next year, where a restructuring has to be done both in terms of budget plans and public investment,” Gavino concluded.

In a written document sent to this newspaper, the San Miguel Federation assured that the work would be delivered 100% within the established period. For San Miguel Consortium Resident Engineer Antonio Hernández and Nueva Rinconada Supervisory Consortium President Alfonso Escobar, the delay of 20 kilometers of pipes will not affect the completion of the mega project. Is this delay common? “When it’s imported (pipes), yes, because you don’t know which port it’s coming from. It’s in God’s hands,” said Escobar.

Interview with Alfonso Escobar

See also  Biden and Germany's Scholz meet amid concerns over Ukraine and China

According to Manuel Barbosa, a civil engineer with experience in planning and design work, the only way to speed up the process is to install pipeline sections simultaneously, which will require more personnel and more budget.

A history of good pro

On August 9, 2021, a few days after the appointment of Kaynar Alvarado and Salatiel Marrufo as Housing Minister and Chief Advisor, Cetabal and the San Miguel Federation signed an agreement for the Nueva Rinconada project. The shares of the consortium are distributed as follows: China Machinery Engineering Corporation (50%), 2H Engineering and Construction SAC (25%), and Sigma SA Contratistas Generales (25%).

Delay. Out of the total 101 km, 20 km of pipelines are missing. (Photo: Peru21)

Although the federation was ratified on April 22, 2021, the agreement was signed in early August. The reason? On May 13 of the same year, the Sino-Peruvian consortium lost the tender for not submitting documents within the established period. However, the company appealed the decision before the State Procurement Tribunal – OSCE and the United Nations Office for Program Services (UNOPS). Later, it was UNOPS that notified the Federation on July 15 that it was withdrawing the project. “This is a bit unusual. Ideally, a good selection process should be carried out with clear rules,” said expert Gavino.

remember

-Cedapal has not yet issued the invoice A fine of S/60 million. It will do so when the company supplies the existing ductile iron pipes in August.

-According to Sedapal, If the delay in delivery of pipelines takes another year, the penalty can reach 10% of the total cost of the work. Work is implemented at 32%.

– “We as citizens cannot continue to tolerate this kind of delay in technical failure,” he said. Karla Gavino, expert in public administration and professor at Universidad Pacifico.

See also  May 1, holiday in Peru: who rests, how much they should pay you to work this day and more | Answers

“This or any other delay may affect the deadline for completing the works,” he said Julio Ramírez Ruiz, Manager of Projects and Missions Sedapal.

“With no comparison or experience, we don’t have the necessary equipment,” he assured. Antonio Hernandez, Resident Engineer of San Miguel Federation.

150 thousand people to be accessed drinking water By First timeY 200 thousand people Excellent sewerage service.

Chronology

– 22 April 2021: Consorcio San Miguel won the award for the Nueva Rinconada project

– 13 May 2021: Consorcio San Miguel loses the tender

– 15 July 2021: Consorcio San Miguel restores good pro

– 29 July 2021: Geiner Alvarado has been appointed Minister of Housing, Construction and Health

– August 2, 2021: Salatadiel Marrufo has been appointed as the head of the Advisory Cabinet of the Ministry of Housing, Construction and Sanitation.

– 9 August 2021: Agreement signed between Consorcio San Miguel and Sedapal

– August 12, 2021: An agreement was signed between the Nueva Rinconada Supervisory Consortium and Cetabal

– August 24, 2021: Cedapal declared the contract with the Nueva Rinconada Supervisory Federation null and void due to its disqualification from the OSCE.

– September 28, 2021: The Nueva Rinconada Federation presents a precautionary measure that enables it to participate and contract with the state.

– November 23, 2021: The Nueva Rinconada Federation renews its contract with Cetabal